Grade separations are proposed in Wake Forest at Rogers Road (S.R. 2052) and Ligon Mill Road (S.R. 2044).
Rogers Road (S.R. 2052) - STIP Project P-5707
Construct a bridge over the CSX S-line railroad Project Schedule
- Due to Right of Way Acquisition challenges construction letting has been delayed.
- Construction anticipated to begin in August 2025.
- Construction expected to take 3 years.
- Utility relocations have begun in several areas along the project where ROW has been acquired.
Estimated Costs
- Right of Way and utility relocation $14,600,000+;
- Construction $42,500,000
The project proposes to construct a bridge on Rogers Road (S.R. 2052) over the CSX S-line railroad in the same location as the existing at-grade crossing.
Current plans include an on-site detour during construction.

Ligon Mill Road (S.R. 2044) - SPOT Project R150048
Construct a bridge over the CSX S-line railroad Project Schedule
- To be determined based on future funding
The project proposes to construct a bridge on Ligon Mill Road (S.R. 2044) over the CSX S-line railroad. The current design shifts Ligon Mill Road approximately 130 feet south, and provides a new entrance to the Smith Creek neighborhood at Steeple Run Drive.
Current plans allow for the existing at-grade crossing to remain open during construction of the new bridge.